VCE General Maths Networks and Decision Mathematics 2024 Exam 1 Mini Test

VCAA General Maths Exam 1

This is the full VCE General Maths Exam with worked solutions. You can also try Mini-Tests, which are official VCAA exams split into short tests you can do anytime.

Number of marks: 8

Reading time: 3 minutes

Writing time: 18 minutes

Instructions
• Answer all questions in pencil on your Multiple-Choice Answer Sheet.
• Choose the response that is correct for the question.
• A correct answer scores 1; an incorrect answer scores 0.
• Marks will not be deducted for incorrect answers.
• No marks will be given if more than one answer is completed for any question.
• Unless otherwise indicated, the diagrams in this book are not drawn to scale.


Networks and decision mathematics - 2024

Question 1 [2024 VCE General Maths Exam 1 Q33]

Consider the following graph.

A graph with 5 vertices and 6 edges, including a loop.

The sum of the degrees of the vertices is

  • A. 10
  • B. 11
  • C. 12
  • D. 13
Correct Answer: C
Click here for full solution
Question 2 [2024 VCE General Maths Exam 1 Q34]

Consider the following graph.

A graph with 6 vertices (A, B, C, D, E, F).

A Eulerian trail through this graph could be

  • A. ABCDEF
  • B. ACBDCFDEF
  • C. BACBDCFDEF
  • D. BDCABCDFCDEF
Correct Answer: C
Click here for full solution
Question 3 [2024 VCE General Maths Exam 1 Q35]

Consider the following graph.

A planar graph.

The number of faces is

  • A. 5
  • B. 6
  • C. 7
  • D. 8
Correct Answer: B
Click here for full solution
Question 4 [2024 VCE General Maths Exam 1 Q36]

Eight houses in an estate are to be connected to the internet via underground cables.
The network below shows the possible connections between the houses.
The vertices represent the houses.
The numbers on the edges represent the length of cable connecting pairs of houses, in metres.

A weighted network graph of houses and cable lengths.

The graph that represents the minimum length of cable needed to connect all the houses is

Four possible minimum spanning trees labelled A, B, C, D.
  • A.
  • B.
  • C.
  • D.
Correct Answer: D
Click here for full solution
Question 5 [2024 VCE General Maths Exam 1 Q37]

The network below represents paths through a park from the carpark to a lookout.
The vertices represent various attractions, and the numbers on the edges represent the distances between them in metres.

A network of paths from a carpark to a lookout with weighted edges.

The shortest path from the carpark to the lookout is 34 m.
This can be achieved when

  • A. \(x = 8\) and \(y = 8\)
  • B. \(x = 9\) and \(y = 7\)
  • C. \(x = 10\) and \(y = 6\)
  • D. \(x = 11\) and \(y = 5\)
Correct Answer: D
Click here for full solution
Question 6 [2024 VCE General Maths Exam 1 Q38]

A connected graph has six vertices and six edges.
How many of the following four statements must always be true?

  • the graph has no vertices of odd degree
  • the graph contains a Eulerian trail
  • the graph contains a Hamiltonian path
  • the sum of the degrees of the vertices is 12
  • A. 1
  • B. 2
  • C. 3
  • D. 4
Correct Answer: A
Click here for full solution
Question 7 [2024 VCE General Maths Exam 1 Q39]

Anush, Blake, Carly and Dexter are workers on a construction site. They are each allocated one task.
The time, in hours, it takes for each worker to complete each task is shown in the table below.

Task 1 Task 2 Task 3 Task 4
Anush 12 8 16 9
Blake 10 7 15 10
Carly 11 10 18 12
Dexter 10 14 16 11

The tasks must be completed sequentially and in numerical order: Task 1, Task 2, Task 3 and then Task 4.
Management makes an initial allocation of tasks to minimise the amount of time required, but then decides that it takes the workers too long.
Another worker, Edgar, is brought in to complete one of the tasks.
His completion times, in hours, are listed below.

Task 1 Task 2 Task 3 Task 4
Edgar 9 5 14 8

When a new allocation is made and Edgar takes over one of the tasks, the minimum total completion time compared to the initial allocation will be reduced by

  • A. 1 hour.
  • B. 2 hours.
  • C. 3 hours.
  • D. 4 hours.
Correct Answer: D
Click here for full solution
Question 8 [2024 VCE General Maths Exam 1 Q40]

A project has 15 activities, \(A–O\), that need to be completed.
The directed network that represents this project is shown below.
The activities are not labelled.

Directed network for a project with 15 activities.

The activity table that could represent this project is

Correct Answer: B
Click here for full solution

End of Multiple-Choice Question Book